Construction

Construction Materials & Items Needed for Hospital Loma de Luz

 

A list of construction projects for 2007

Description of ProjectPriorityEstimate# of workersDuration
Ambulance entrance roof and lighting team high$5,000.0082 weeks
Siding on apartment building - east side   team  high $2,500.00 6 1 week
gutters at joes place and hospital teamhigh $2,000.00 8 1 week
Community Hall - Multi purpose room completion - Projects as required teamhigh $1,000–$5000 4–8 1–2 weeks
Paint walls by gate teamhigh $1,000.00 4–6 1 week
Surgery lights install and redo insulation overhead with AC system team medium $4,000.00 4–6 1 week
Sign program for hospital exterior develop and install team   medium   $2,000.00 4–6 1 week
Diesel containment paint and generator room team medium $1,000.00 4–6 1 week
Temporary Childrens Center house exterior repairs and paint team medium $2,500.00 82 weeks
Triage paint roof inside team medium $500.00 4 1 week
Fence rebuild in front of hospital perhaps vinyl team medium $4,000.00 4 1 week
Garage doors on Joes Bodega team medium $3,000.00 4–6 1 week
Paint interior of nurses dorm team medium $800.00 4 1 week
Paint handrails at apartments team medium $300.00 4 1 week
Guard rail of cable and steel posts along drive by staff housing team low $1,000.00 4–6 1 week
Soffitt for hospital and nurse dorm building* team low $8,000.00 82 weeks

     *lots of metal fabrication is required for this project

Some of these projects could be combined for qualified teams. Painting projects could also be combined.
The number of workers and duration of project are all estimates.
All teams are to be approved through the Cornerstone Foundation process and Mike.

April 2007

Contact missionary Mike Yost at yostmp@lomadeluz.net for more information about specific items.

If you have an item to donate, please contact: cornerstone@ametro.net
Ph./Fax: 228-328-1579 (toll free 877-277-8663)